Meeting held on: Monday 25th February 2013
Location: Cantor 9200
Attendance: JK (Project Manager) LH (Team Member) DW (Team Member)
Apologies: David Ward
No.
|
Raised
by
|
Item
|
|
Action
by
|
1
|
KEN
|
Feed
back
|
Good results on our presentation group happy
all round
|
All
|
2
|
KEN
|
Guide
lines
|
Wrote down a list of things to consider when
creating a presentation
|
JK
|
3
|
DW
|
Apology
|
Apologises
for not bring in work
|
DW
|
4
|
LH
|
Ideas
|
LH
reveals ideas JK and DW supports ideas and thinks its very good
|
ALL
|
5
|
JK
|
Ideas
|
JK reveals ideas and LH thinks the 2nd
passage chosen is very visual and can work
|
ALL
|
6
|
JK
|
Ideas
|
Decided that we should combine the 2 ideas
|
ALL
|
7
|
ALL
|
Idea
|
Combined the idea to create one animation but
in three parts
|
ALL
|
8
|
JK
|
Idea
|
Suggest we split the idea into three so each of
us can do story boards and visuals for next week so we have a plan
|
ALL
|
9
|
DW
|
Argues
|
Argues that we don’t need a storyboard for part
three as it won’t be animated however as JK explains that as it’s a prototype
it will have all the development except the animation will not be done
|
ALL
|
10
|
DW
|
Argues
|
DW says that if it makes JK happy that the
story board will be done
|
DW
|
11
|
ALL
|
Timetable
|
Lists out all the task and mini deadlines that
need to be completed in order to meet the final dead line
|
ALL
|
12
|
JK
|
Meeting
|
Monday 4th March 2013
|
ALL
|