Monday, 8 April 2013
Friday, 5 April 2013
Animation Progress
The animation is almost complete. Traditional techniques were replicated using digital software, such as Adobe Flash, Photoshop and Premiere, to create the animation’s chosen design style in a short time period to a high standard. It was very important to create the piece to meet the expectations of the client in the time frame provided. Both hand drawn animation and computer ‘tweened’ animation are being used to produce the animation. I am very happy with the outcome yet it has taken longer than expected. However the animation will still be completed in plenty of time for myself to be able to animate and code the interactive section.
Saturday, 23 March 2013
Meeting 11
Meeting held on: Monday 18th March 2013
Location: Cantor 9200
Attendance: JK (Project Manager) LH (Team Member) DW (Team Member)
Apologies: None
|
No.
|
Raised
by
|
Item
|
|
Action
by
|
|
1
|
JK
|
Tasks
|
Checks to see if every one is on schedule
Also make sure everyone has documents and work
that they need from each to work on over the Easter period
|
All
|
|
2
|
JK
|
Tasks
|
As DW was absent last week he share the work he
had to give ready to insert into the presentation
|
DW JK
|
|
3
|
All
|
Tasks
|
Everyone
gets on with task they have been given
DW: Create 3d rabbit hole for part one
And for part two
JK: Finish any alterations to the interactive
world and give to LH
LH: Finish any alteration for part one of
animation and start to make interactive world interactive
|
All
|
|
4
|
JK
|
Check up
|
Checks
every one knows what they have to get done by the time we return after Easter
|
All
|
|
5
|
JK
|
Meeting
|
Next meeting will be held on Monday 8th
April 2013
Unless a meeting is need over the Easter period
we can arrange one
|
All
|
Meeting 10
Meeting held on: Monday 11th March 2013
Location: 9200
Attendance: JK (Project Manager) LH (Team Member)
Apologies: DW (Team Member) Absent
|
No.
|
Raised
by
|
Item
|
|
Action
by
|
|
1
|
Jk
|
Task
given
|
Checked to see if me and LH were up to schedule
with the tasks and whether we are hitting deadlines
|
All
|
|
2
|
JK
|
Tasks
|
Showed my efforts of creating the world was
struggling a bit
|
JK
|
|
3
|
LH
|
Tasks
|
On
schedule and proved to show good work
|
LH
|
|
4
|
LH
|
Flash
|
LH
decided to help JK to show her bit more about flash
|
All
|
|
5
|
JK
|
Flash
|
Appreciated the help off LH and JK has a better
understanding so getting on with creating and finishing the interactive world
for next week
|
JK
|
|
6
|
LH
|
Flash
|
Carry’s on finishing part one of the animation
for next week
|
LH
|
|
7
|
JK
|
Meeting
|
Next meeting for Monday 18th March
2013
|
All
|
Monday, 18 March 2013
Idea Development
We have recently been developing and expanding upon the ideas for our project, we divided our plans between the three of us and created storyboards for every section of the project. The section which I pre-visulized was an extract from the story which would be animated, viewers would be able to click a link which would lead them to an animation created in the paper cut out style which is being used consistently throughout the project, this would then have a voice over reading an extract from the story. The purpose of this would be to intrigue the viewr and make them want to see more of the book.
After creating the first proposed shot shown above, I decided that it was a strange angle and so developped the idea further by storyboarding an alternative begining, with a different angle.
Thursday, 14 March 2013
Introductory Animation: Animatic
Here's the Animatic for the Introductory animation which i'll shortly be starting on. Ill get you feeback in our meeting, either that or post a comment.
Monday, 4 March 2013
Meeting 9
Meeting held on: Monday 4th March 2012
Location: Cantor 9200
Attendance: JK (Project Manager) LH (Team Member) DW (Team Member)
Apologies: None
|
No.
|
Raised
by
|
Item
|
|
Action
by
|
|
1
|
JK
|
Deadline
|
Sees the groups work which is set for today,
everyone gives feedback on others work and gives pointers to consider
|
All
|
|
2
|
LH
|
Work
|
Great Animatics produced needs finishing off a
few things changed around
|
LH
|
|
3
|
JK
|
Work
|
Great
shot of layout and what the ‘world’ will look like needs to know be created
with textures
|
JK
|
|
4
|
DW
|
Work
|
Great
storyboard with the passage needs to look at layouts and camera angels
|
DW
|
|
5
|
JK
|
Deadline
|
Sets Deadlines for all Members for Monday 11th
March 2013
|
All
|
|
6
|
JK
|
Goals
|
1)
Composting of table
2)
Camera Angles (Birds eye view)
3)
Polish up
4)
Play Around with 3d Rabbit hole
5)
Screen shot everything for power point
|
DW
|
|
7
|
JK
|
Goals
|
1)
Finish Animatics with 2 possible endings
2)
Review, Changes?
3)
Screen Shot
4)
Layout
5)
Start Animation
6)
Screen Shot everything for power point
|
LH
|
|
8
|
JK
|
Goals
|
1)
Start Power point
2)
Play around with Flash
3)
Animatics (Start)
4)
Meeting documented
5)
Screen Shot everything for power point
|
JK
|
|
9
|
JK
|
Review
|
Review LH work and give ideas to go away with
|
All
|
|
10
|
JK
|
Goals
|
Check everyone’s knows what they are doing for
next week
|
All
|
|
11
|
JK
|
Meeting
|
Next Meeting Monday 11th March 2013
|
All
|
Subscribe to:
Posts (Atom)