Meeting held on: Monday 25th February 2013
Location: Cantor 9200
Attendance: JK (Project Manager) LH (Team Member) DW (Team Member)
Apologies: David Ward

No.
Raised by
Item

Action by
1
KEN
Feed back
Good results on our presentation group happy all round
All
2
KEN
Guide lines
Wrote down a list of things to consider when creating a presentation
JK
3
DW
Apology
 Apologises for not bring in work
DW
4
LH
Ideas
LH reveals ideas JK and DW supports ideas and thinks its very good
ALL
5
JK
Ideas
JK reveals ideas and LH thinks the 2nd passage chosen is very visual and can work
ALL
6
JK
Ideas
Decided that we should combine the 2 ideas
ALL
7
ALL
Idea
Combined the idea to create one animation but in three parts
ALL
8
JK
Idea
Suggest we split the idea into three so each of us can do story boards and visuals for next week so we have a plan
ALL
9
DW
Argues
Argues that we don’t need a storyboard for part three as it won’t be animated however as JK explains that as it’s a prototype it will have all the development except the animation will not be done
ALL
10
DW
Argues
DW says that if it makes JK happy that the story board will be done
DW
11
ALL
Timetable
Lists out all the task and mini deadlines that need to be completed in order to meet the final dead line
ALL
12
JK
Meeting
Monday 4th March 2013